İZSU Urla Wastewater Treatment Plant

İZSU Urla Wastewater Treatment Plant

Work Done

İZSU Urla 100.000 kişilik arıtma tesisi altyapı işleri ve deniz deşarj hatlarının yapılması ve devreye alınması işleri Q1000 mm boru.

Firm

İZSU

Location

İzmir

History

2009-2011

Project Completion Rate 100%

About the Project

Between 2009 and 2011, AYC Group carried out the infrastructure works for the Urla 100,000-person wastewater treatment plant and the construction and commissioning of the sea discharge lines within the scope of İZSU (Izmir Water and Sewerage Administration) in Izmir. The project encompassed the creation of the treatment plant infrastructure and the technical applications for the safe disposal of wastewater.