İZSU Urla Wastewater Treatment Plant
Work Done
İZSU Urla 100.000 kişilik arıtma tesisi altyapı işleri ve deniz deşarj hatlarının yapılması ve devreye alınması işleri Q1000 mm boru.
Firm
İZSU
Location
İzmir
History
2009-2011
Project Completion Rate
100%
About the Project
Between 2009 and 2011, AYC Group carried out the infrastructure works for the Urla 100,000-person wastewater treatment plant and the construction and commissioning of the sea discharge lines within the scope of İZSU (Izmir Water and Sewerage Administration) in Izmir. The project encompassed the creation of the treatment plant infrastructure and the technical applications for the safe disposal of wastewater.